Objective
Full scope installation + Completions on GWA mine site pipeline in remote Western Australia – GWA 6MW machines.
Project:
Location:
Date:
Kathleen Valley
Western Australia
Challenges
Site Remoteness, being mine site much higher safety performance expectations. Heat – regularly getting extreme temperatures, which translated to over 50 degrees C in the towers. New turbines platform – this is Goldwind 6MW platform – first windfarm completed in AUS.
Value to Client
Client impressed with the level of skilled resources Aurora ARC provided to site. Client was very happy with quality of works, supervision level and how well the team worked on site. Remaining 4 projects expected to go well.