Moray East OWF Project

At a Glance

Challenges

Client required skilled Rope Access Labour for the offshore construction phase completions on Moray East.

Value to Client

Provision of skilled labour, with experience in technical specialised access to complete work including over side works.

All works signed off by third party NACE L3 Inspectors.

blue alert sign

Objective

Attend the Moray East Offshore Wind Farm to carry out remedial repairs of marine grade coatings:

The primary work scope was to carry out touch up painting repairs on the damaged areas caused during lifting of the sub structures.

This included padeye recoating, grating repairs, handrail repairs according to pre-determined snagging list.

Key Details

Project:
Moray EAST OWF
Location:
Scotland, UK
Date:
March 2019 - September 2020
blue tick

Solution

1

Operations division mobilised multiskilled technicians including Platers, Riggers, Inspectors and painters most of whom were trained internally at our Inverness based training facility.

2

The OWF was fully operational in 2021 and because of the successful work carried out previously, we were selected to carry out further remedial works on the OWF including installation of bird scarers, crane tilt surveys and cleaning of guano.  

3

Team included 6xL3 supervisor and 6x Level 1 and 2 Operatives to safely carry out this scope of work.

Back to Case Studies

Click below to return to the case studies page
Case Studies Library
Aurora logo with white text

Entre em contato conosco

Se você quiser manter contato, preencha o formulário abaixo e responderemos à sua consulta (geralmente no próximo dia útil).

Obrigado! Seu envio foi recebido!
Opa! Algo deu errado ao enviar o formulário.