Wet Gas Pipework (R&M)

blue alert sign

Objective

This project was to replace 300 meters of existing process gas pipework, transitioning from carbon steel to duplex material, within a 16-week timeframe.

Project:
Location:
Date:
Wet Gas Pipework Replacement
N/A
March 2022

Challenges

Fast track project with an extremely tight schedule (16 weeks). Complex logistics due to offshore construction. Technical challenges associated with the material transition from carbon steel to duplex.

Value to Client

·      Enhanced durability and performance of gas pipework.

·      Improved corrosion resistance, reducing maintenance needs and extending the lifecycle of the pipework.

·      Minimised downtime due to efficient and timely project execution.

blue tick

Solution

·       Developed detailed engineering deliverables including 23 piping isometrics, 23 pipe support configurations, and 14 P&IDs.

1

·       Conducted a341-hour intensive stress engineering phase to ensure the pipework could withstand operational conditions.

2
3

·       Prepared comprehensive construction work packs for efficient offshore execution, ensuring adherence to safety protocols and quality control.

Back to Case Studies

Click below to return to the case studies page
Case Studies Library
Aurora logo with white text

Global Experts. Proven Results. Reach Out Today.

Looking to optimise your energy assets? Our experts are here to help.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.