Wet Gas Pipework (R&M)

At a Glance

Challenges

Fast track project with an extremely tight schedule (16 weeks). Complex logistics due to offshore construction. Technical challenges associated with the material transition from carbon steel to duplex.

Value to Client

This project was to replace 300 meters of existing process gas pipework, transitioning from carbon steel to duplex material, within a 16-week timeframe.

blue alert sign

Objective

This project was to replace 300 meters of existing process gas pipework, transitioning from carbon steel to duplex material, within a 16-week timeframe.

Key Details

Project:
Wet Gas Pipework Replacement
Location:
N/A
Date:
March 2022
blue tick

Solution

1

·       Developed detailed engineering deliverables including 23 piping isometrics, 23 pipe support configurations, and 14 P&IDs.

2

·       Conducted a341-hour intensive stress engineering phase to ensure the pipework could withstand operational conditions.

3

·       Prepared comprehensive construction work packs for efficient offshore execution, ensuring adherence to safety protocols and quality control.

Back to Case Studies

Click below to return to the case studies page
Case Studies Library
Aurora logo with white text

Entre em contato conosco

Se você quiser manter contato, preencha o formulário abaixo e responderemos à sua consulta (geralmente no próximo dia útil).

Obrigado! Seu envio foi recebido!
Opa! Algo deu errado ao enviar o formulário.